Contracts for 10 new stadia are expected to be awarded by the end of November, with construction teams due to move on to the sites before the end of December, Sports and Recreation Minister Kofi Iddie Adams has said.
Speaking to TV3 during Thursday’s presentation of the 2027 Budget Statement in Parliament, Mr Adams said locations had been confirmed for every facility and the preparatory work was complete.
“Sites have been identified and everything is done. Hopefully, by the end of this month, the contracts will be awarded and contractors will mobilise to move to site before the end of December,” he said.
The government has increased its stadium programme from six venues to 10, going beyond the number promised in its manifesto.
Mr Adams said the decision followed a review of how the programme would be delivered. The initial plan was to begin three projects this year and start another three at a later stage, but the time required to appoint consultants and complete the contract-award process led the government to pursue all 10 projects together.
“In the manifesto we promised six. When we came in and reviewed the situation, we promised to start three this year. But going into the fold, we realised we were starting three this year and waiting to start another three.
“The process of going through to get consultants and all the processes to award contracts takes quite some time. So it is better to procure the 10 at a go,” he said.
Sites and capacities
The proposed stadia will be spread across Western North, Ahafo, Bono East, Savannah, North East, Upper East, Upper West and Oti.
The programme also includes a stadium in Ho in the Volta Region and another at Abesim in the Bono Region.
Specific locations named by the minister include Nyamibechere, between Mim and Goaso, in Ahafo; Oforikrom, near Techiman, in Bono East; Damongo in Savannah; Nalerigu in North East; Bolgatanga Bukere in Upper East; Wa in Upper West; and Gwama in Oti Region.
The venues will not all be the same size. Depending on their location, they will include stadia with capacities of 5,000, 7,000 and 10,000 spectators.
Mr Adams said the projects had already passed several stages of preparation. Consultants had been appointed, designs completed and Bills of Quantities prepared, while the projects had also gone through the Public Procurement Authority process.
“All these 10, we have gone through the processes, consultants have been procured, designs have been done, the BOQs have been done, we’ve gone through PPA and we are in the process of awarding the contracts,” Mr Adams said.
The stadium programme is part of the government’s wider plan to expand sporting infrastructure and improve access to facilities across the country.