Homes and businesses in parts of Kumasi, the Western Region and Accra are facing power cuts after illegal chainsaw operators brought down a tree onto a major transmission line and the Electricity Company of Ghana (ECG) carried out transformer upgrades.
The Ghana Grid Company (GRIDCo) said its 330kV Aboadze–Anwomaso line tripped late on Wednesday afternoon, disrupting electricity supplies in the Western and Ashanti regions after days of scheduled regional outages.
The failure forced system operators to reduce the amount of power delivered to parts of Kumasi. GRIDCo engineers later found that a large tree felled by illegal chainsaw operators had landed on the transmission line.
Emergency teams were repairing the damaged section, GRIDCo said, adding that it had apologised to affected customers. In September, the company took its Right-of-Way sensitisation campaign to the Ashanti Region in an effort to prevent encroachment along transmission corridors.
In Accra, ECG has attributed two weeks of intermittent power cuts to transformer upgrades and unexpected faults. Separate maintenance work on Thursday also left 19 communities in the Central Region without electricity between 9:00 am and 4:00 pm.
ECG General Manager for External Communications Dr Charles Nii Ayiku Ayiku told a radio interviewer on Thursday that crews were installing or replacing transformers in Kwabenya, Adenta, Boteyman, Teshie and Dodowa, covering the Accra East and Accra West areas.
He said the scheduled work had been compounded by what he called “the emergency ones” – faults caused by overloaded transformers and sudden failures across the network.
A damaged underground cable at Ashongman Villa also disrupted supply to Ashongman Estate, Ashongman Mangoase, Ashongman Veggies, the Atomic Hospital enclave, the Atomic Theatre area and nearby streets.
The disruption in Ashanti occurred while GRIDCo was carrying out a separate project on the Anwomaso–Ahodwo transmission line in Kumasi. The upgrade was 70 per cent complete and is intended to ease local supply bottlenecks when commissioned.
Dr Ayiku apologised for the interruptions affecting customers in Accra. He said the completion of the new Katamanso substation would provide “some huge relief in these areas” by reducing pressure on strained lines.
In the Western Region, where the Aboadze–Anwomaso corridor begins, ECG had previously assured residents that it was working to restore regular electricity supplies after persistent local faults.
GRIDCo has increased enforcement along its transmission corridors in Ashanti. The company had earlier given people encroaching on protected land beneath high-tension lines at Ejisu 30 days to leave.
The company said electricity supplies to the affected parts of Kumasi and the Western Region would return to normal after crews removed the fallen timber and completed repairs to the 330kV line.
Customers experiencing unannounced outages or fallen cables can contact ECG’s 24-hour call centre on 0302 611611 or check updates on ECG’s website.