MP demands clarity over Saglemi delays and Ghana’s GH¢2.5bn housing plans

Techiman South MP Martin Adjei-Mensah Korsah has questioned the government’s revised targets for the Saglemi housing project, inconsistencies in Housing Fund figures and the progress of flood-control works under Ghana’s GH¢2.5 billion Works, Housing and Water Resources budget for 2027.

The allocations, set out in paragraph 1556 of the 2027 Budget Statement, include GH¢820 million for water systems in Tamale, Yendi and Damongo, as well as GH¢75 million for other water projects.

A further GH¢500 million is earmarked for the Housing Fund, with GH¢103 million for district housing, GH¢250 million for the Blekusu coastal project and GH¢500 million for other ongoing sea defence works.

Mr Adjei-Mensah Korsah, the Ranking Member of Parliament’s Works and Housing Committee, welcomed the funding in a written review of the sector estimates published on Wednesday, but said previous government commitments had not been properly reconciled.

Saglemi and rental housing

He compared the 2027 proposals with paragraph 524 of the 2026 Budget, which had forecast that 8,000 Saglemi units would be habitable during the first phase in 2026.

The revised plan in paragraph 1310 of the 2027 statement is for 1,506 homes to be completed by the end of 2027. The first 700 are scheduled for March, with the remaining 806 due by December. Mr Adjei-Mensah Korsah said the document did not explain the reduction from the earlier 8,000-unit target.

Works and Housing Minister Ahmed Ibrahim told Parliament on 18 November that contractors had resumed work at Saglemi through a joint venture approved by the Attorney-General’s Office following a Deloitte Ghana selection process. He said the arrangement would avoid creating new debt for the state.

The MP also raised concerns about 800 affordable flats at Tema Community 26 under the Kpone project. The development was 80 per cent complete despite an earlier ministerial target for completion in September 2026.

He noted that the 2026 Budget had promised an additional 10,000 Rent-to-Own beneficiaries. However, the 2027 statement records 917 tenants supported by September 2026 and 5,647 beneficiaries in total under the separate National Rental Assistance Scheme.

Mr Adjei-Mensah Korsah also highlighted a discrepancy over Housing Fund financing. Paragraph 1557 cites GH¢500 million, while Appendix 4A lists GH¢1 billion. The latter figure corresponds with President John Mahama’s October announcement directing GH¢1 billion towards a GH¢3 billion revolving fund.

He asked the ministry to explain the GH¢500 million provided for district housing and Akosombo spillage resettlement in 2026, given that the 2027 budget contains a GH¢103 million line for district housing.

Flood and coastal works

Paragraph 1299 says GH¢226 million was reallocated during the 2026 rains for 137 emergency desilting contracts and 76 flood-control construction projects. Although 118 desilting works have been completed, only 37 of the 76 construction contracts are listed as ongoing.

Mr Adjei-Mensah Korsah requested clarification on the remaining projects and on how flood warnings are linked to drain maintenance.

The budget says the eight-kilometre Blekusu defence project in Ketu South is more than 50 per cent complete. A separate GH¢685 million has been allocated for Keta coastal works under the WACA programme through the Environment Ministry.

Completion of Blekusu is scheduled for 2028, while 295 resettlement homes for Akosombo dam spillage victims in Central, North and South Tongu are due in 2027.

He also said planned White Volta dredging to address Bagre Dam spillage should be based on hydraulic and sediment studies, and called for sector contracts to include verifiable local training.

You may like

Poor contractor performance undermined Akufo-Addo’s Year of Roads, says Agbodza

More than 5,000 Ghanaian nurses and midwives inducted with call for better working conditions

Jimmy Odukoya ordered to appear in Lagos court over alleged breach of church injunction

Ghana Education Service recruitment portal to open at 8pm with 7,000 teaching jobs

Accra businessman granted GH¢400,000 bail in disputed Osu property case

20 held over alleged streetlight thefts across Greater Accra, says Linda Ocloo

Public notice