Ghana’s planned 2,000-megawatt nuclear power plant could cost between US$15 billion and US$30 billion to build, according to the Africa Centre for Energy Policy (ACEP).
The estimate is contained in ACEP’s analysis of the 2027 Budget Statement, published on Wednesday, as the government seeks US financial support for the country’s first state-owned nuclear facility.
ACEP based the projected cost on comparable nuclear projects overseas. A 462MW small-reactor project in the United States rose in price from US$5.3 billion to US$9.3 billion during 2023.
At Egypt’s El Dabaa plant, reactors producing between 1,100MW and 1,200MW cost about US$7.5 billion each. The equivalent units at Vogtle in the United States cost US$15 billion each.
The financing arrangements at El Dabaa also illustrate the potential burden on Ghana’s public finances. A state loan from Moscow covered 85% of the Egyptian project’s cost and is repayable over 22 years at an interest rate of 3%.
ACEP said that arrangement demonstrated the scale of sovereign liability that vendor financing can create. Ghana is pursuing its own 2,000MW project with Russia.
Funding and deadlines
The 2027 Budget allocates US$200 million over two years for nuclear readiness activities. The funding is scheduled to cover the period from January 2027 to December 2028, with the objective of concluding a deal to engineer, procure, construct and finance the plant.
ACEP acknowledged that committing funding on this scale indicated serious long-term intentions for low-carbon baseload electricity. However, it said the budget did not provide an annual disbursement schedule.
The budget states that the plant will be fully owned by the Ghanaian state and financed by foreign partners, but does not outline the terms of that financing.
The centre also raised questions about whether the process for choosing a vendor would remain competitive. Ghana’s agreement with Russia came after earlier framework agreements with American and Chinese vendors.
Ghana’s Foreign Minister has separately sought United States cooperation on nuclear energy, while Russia has offered to assist with the construction of the 2,000MW facility.
ACEP said the December 2028 target would also require Parliament to pass the Nuclear Power Corporation Bill, as well as the acquisition and characterisation of the plant site.
It called on the government to set out clearly how the legal, procurement and financing stages would be sequenced, so the programme could be delivered within the proposed timetable.
ACEP’s wider assessment of the budget was that its overall direction was appropriate, but that success would depend on careful programme design and spending.
Without a credible financing plan, the organisation warned that allocating US$200 million to readiness work could tie up public funds in a timetable unable to withstand the process of reaching financial close.