The Electricity Company of Ghana (ECG) says frequent power outages affecting parts of the Western Region are being caused by faults in underground cables, rather than what is commonly referred to in Ghana as “dumsor”.
Awal Boye, ECG’s Western Regional Public Relations Officer, said the company was working to restore electricity to affected communities but had encountered difficulties reaching some of the damaged cables.
Speaking on Connect FM’s Midday News, Mr Boye apologised to customers for the disruption and said load shedding had been introduced in some areas to maintain access to electricity.
“We have deployed load shedding in some areas to ensure that consumers have access to electricity,” he said.
He explained that repair work had been slowed because structures had been built along the routes of the buried cables. In some cases, shops had been erected directly above the infrastructure.
“Some underground cables have been built over, while stores have also been erected on routes where our cables are buried, making repairs very difficult,” he disclosed.
Mr Boye described the work as demanding but said ECG was increasing its efforts to deal with the most serious faults by the end of the week.
“Repairing underground cables is a tedious process, but we are working intensively to resolve the major faults by the close of this week. We appeal to residents to bear with us,” he said.
He said the company could not publish a fixed schedule for the outages because they were the result of faults affecting load shedding, rather than planned maintenance.
“We cannot provide a fixed timetable for the outages because they are caused by faults on the load shedding and are not part of a planned ECG maintenance schedule,” he added.
Residents in the affected communities have been asked to remain patient while repair teams work to restore a stable supply.
ECG has not given a precise date for resolving all the outstanding problems. Mr Boye said the immediate priority was to fix the major faults before addressing the minor ones, while expressing hope that the electricity supply would be stabilised by the close of the week.
The repeated interruptions have prompted differing reactions from residents in parts of the metropolis. Some have described the situation as dumsor, while others have rejected that description.
One resident said the outages reflected poor performance by ECG and suggested they could create the impression of an attempt to undermine the government.
“I would not describe this as dumsor. I believe ECG is simply not performing its duties effectively, and the situation makes it appear as though there is a deliberate attempt to sabotage the government,” the resident said.
Others said the cuts were disrupting their everyday lives, particularly during the current extreme heat.
“The heat is already unbearable, and when the lights go off, it becomes even more difficult to cope, especially at night,” another resident said.
Residents have also urged ECG to deal with the faults urgently and restore a dependable electricity supply to the affected communities.