The road connecting the Obetsebi Lamptey Interchange with the Metro Mass area at Pamprom Junction is expected to reopen between 15 and 20 December 2026, with the first phase of the drainage improvement works now about 90% complete.
Cephas Ofori, Project Manager of the Greater Accra Resilient and Integrated Development (GARID) Project, said contractors were working towards the mid-December deadline to return the route to motorists.
The outstanding work includes backfilling and reinstating the road pavement, which must be completed before traffic can resume along the affected section.
Speaking on Channel One News on November 21, Ofori said reopening the road would help reduce congestion around the interchange during the Christmas period.
“We are targeting around the 15th to 20th of December. That is when we are opening the road to the motoring public, from Obetsebi Lamptey through to the Metro Mass area, which we call the Pamprom Crossing,” he said.
He said the main construction operations for the first phase had been completed. These included demolition, excavation, the building of base walls and the installation of cover slabs.
Work has also begun on the second phase of the project, which covers the route from Pamprom Crossing to First Light.
The westbound carriageway of the Dr Busia Highway, starting from Pamprom Junction, was closed on September 7 to allow the drainage works to be carried out under the GARID Project. The initial schedule had set November as the completion point for the first phase.
The project forms part of efforts to improve drainage infrastructure in the area, while the closure has required traffic to be managed through alternative routes and other arrangements.
Traffic measures
GARID Project Communications Specialist Philip Dunyo said public education and the availability of alternative routes had helped limit the effect of the construction on motorists.
He said drivers had, in general, followed the traffic management measures put in place before and after the road closure.
According to Dunyo, compliance with those arrangements had helped maintain the movement of vehicles and avoid major gridlock around the interchange during the construction period.
The planned reopening between 15 and 20 December would therefore restore access along the section from Obetsebi Lamptey to Pamprom Crossing, while construction continues on the next part of the drainage project towards First Light.